Solar Wheeling and Banking Charges in Tamil Nadu 2026
    Back to Blog
    Policy

    Solar Wheeling and Banking Charges in Tamil Nadu 2026

    8 min read
    On This Page

    For consumers exploring open access solar in Tamil Nadu -- purchasing solar power from an off-site generator and having it delivered through the TANGEDCO/TANTRANSCO grid -- understanding wheeling charges, banking provisions, and transmission losses is essential. These charges determine the true delivered cost of open access solar and, ultimately, whether it saves you money compared to drawing power directly from TANGEDCO.

    This guide provides the detailed 2026 charge structure, explains how each component works, and walks through real cost calculations so you can evaluate open access solar for your facility.


    What Are Wheeling and Banking Charges?

    Wheeling Charges

    When solar power is generated at a remote location and consumed at your premises, it travels through TANGEDCO's distribution network (and possibly TANTRANSCO's transmission network). Wheeling charges compensate TANGEDCO for the use of their infrastructure to deliver this power.

    Think of it as a delivery fee. You are buying electricity from a solar plant, but TANGEDCO's wires are carrying it to your meter. They charge for this service.

    Transmission Charges

    If the solar plant and your consumption point are in different TANGEDCO distribution circles, the power also travels through TANTRANSCO's high-voltage transmission network. Transmission charges cover this inter-circle transport.

    Banking Charges

    Solar generation peaks during midday but your consumption may be spread across all 24 hours. Banking allows you to inject surplus solar power into the grid during peak generation and draw it back during non-generation hours (evening, night). The grid essentially acts as a battery. Banking charges compensate TANGEDCO for this storage-like service.


    2026 Charge Structure in Tamil Nadu

    The following rates are based on the latest TNERC tariff orders applicable for the 2025-26 period. Rates are subject to revision in future tariff orders.

    Wheeling Charges

    Voltage LevelWheeling Charge (per unit)Applicable To
    HT (11 kV / 22 kV)Rs 0.45-0.55Distribution within a single circle
    EHT (33 kV / 66 kV)Rs 0.35-0.45Distribution at extra-high tension
    Embedded generation (same substation)Rs 0.20-0.30Generator and consumer on same feeder

    Transmission Charges

    ComponentRate (per unit)Notes
    TANTRANSCO transmissionRs 0.40-0.60Applicable when power crosses distribution circles
    SLDC (State Load Despatch Centre) schedulingRs 0.05-0.10Applied to all open access transactions

    Banking Charges

    ComponentRateNotes
    Banking charge2% of banked energy (in kind)Deducted from withdrawable banked units
    Banking periodApril to March (financial year)Surplus resets annually
    Unutilised banked energy compensationRs 2.00-2.50 per unitPaid at year-end for any undrawn surplus

    Cross-Subsidy Surcharge (CSS)

    Consumer CategoryCSS Rate (per unit)Applicability
    HT Industrial (HT-1)Rs 1.00-1.30Third-party open access only
    HT Commercial (HT-2)Rs 1.20-1.50Third-party open access only
    Captive/Group CaptiveExemptAs per Electricity Act 2003

    Additional Surcharge

    ComponentRate (per unit)Notes
    Additional surchargeRs 0.25-0.50Applicable to third-party open access; represents stranded cost recovery

    Transmission and Wheeling Losses

    In addition to per-unit charges, open access consumers bear energy losses -- the physical energy lost as heat during transmission through wires and transformers. These losses are deducted "in kind," meaning if you inject 1,000 units at the solar plant, fewer units arrive at your meter.

    Loss ComponentTypical PercentageImpact on 1,000 Units Injected
    Transmission losses (TANTRANSCO)3-4%30-40 units lost
    Distribution wheeling losses (TANGEDCO)5-7%50-70 units lost
    Total losses8-11%80-110 units lost

    For every 1,000 units your solar plant generates, approximately 890-920 units are available for your consumption (before banking charges).


    Complete Cost Calculation: Captive vs Third-Party

    Scenario 1: Captive/Group Captive (26% equity in solar plant)

    A factory in Coimbatore's SIDCO estate with 200 kW demand, drawing solar from a 1 MW solar plant in which it holds 26% equity:

    ComponentRateMonthly Cost (40,000 units)
    Solar generation costRs 2.80/unitRs 1,12,000
    Wheeling charges (HT)Rs 0.50/unitRs 20,000
    Transmission chargesRs 0.50/unitRs 20,000
    SLDC schedulingRs 0.07/unitRs 2,800
    CSSExemptRs 0
    Additional surchargeExemptRs 0
    Losses (10%)4,000 units equivalentRs 11,200
    Total delivered costRs 4.15/unitRs 1,66,000

    Compare with TANGEDCO HT Industrial: Rs 7.00/unit x 40,000 = Rs 2,80,000

    Monthly savings: Rs 1,14,000 | Annual savings: Rs 13,68,000

    Scenario 2: Third-Party PPA (No equity in solar plant)

    The same factory purchasing solar from a third-party developer under a 25-year PPA:

    ComponentRateMonthly Cost (40,000 units)
    PPA tariffRs 3.50/unitRs 1,40,000
    Wheeling chargesRs 0.50/unitRs 20,000
    Transmission chargesRs 0.50/unitRs 20,000
    SLDC schedulingRs 0.07/unitRs 2,800
    CSSRs 1.15/unitRs 46,000
    Additional surchargeRs 0.35/unitRs 14,000
    Losses (10%)4,000 units equivalentRs 14,000
    Total delivered costRs 6.42/unitRs 2,56,800

    Compare with TANGEDCO HT Industrial: Rs 7.00/unit x 40,000 = Rs 2,80,000

    Monthly savings: Rs 23,200 | Annual savings: Rs 2,78,400

    The savings under third-party PPA are much thinner due to CSS and additional surcharge. However, as TNERC progressively reduces CSS (which it has been doing), the third-party model becomes increasingly viable.


    Banking: How It Works in Practice

    Tamil Nadu's banking provision is one of the most generous in India for solar open access consumers. Here is how it works month by month:

    Example: 500 kW Solar Plant, 400 kW Consumer Load

    Time PeriodSolar GenerationConsumer DemandAction
    6 AM - 9 AM200 units400 unitsDraw 200 from grid + 200 from solar
    9 AM - 3 PM600 units400 unitsConsume 400 from solar, bank 200
    3 PM - 6 PM200 units400 unitsConsume 200 from solar, withdraw 196 from bank (2% charge)
    6 PM - 6 AM0 units300 unitsWithdraw from bank or draw from grid

    Annual Banking Settlement

    At the end of the financial year (March 31):

    • Any banked energy that has not been withdrawn is settled by TANGEDCO at the buyback rate (Rs 2.00-2.50/unit)
    • This rate is significantly lower than the generation cost, so you want to minimise year-end surplus
    • Proper system sizing (matching generation to consumption) maximises the financial benefit

    Strategic Considerations for Tamil Nadu Open Access Consumers

    1. Captive vs Third-Party: The Equity Decision

    The CSS exemption for captive consumers saves Rs 1.00-1.50 per unit. For a factory consuming 50,000 units/month, that is Rs 50,000-75,000/month or Rs 6-9 lakh/year. This saving often justifies the equity investment in a solar plant.

    2. Group Captive for Mid-Sized Consumers

    If your demand is 100-500 kW, investing in your own solar plant may not be economical. Group captive arrangements allow you to hold proportional equity in a larger plant, accessing better economies of scale while enjoying CSS exemption.

    3. Hybrid Strategy: Rooftop + Open Access

    Install rooftop solar to the maximum extent your roof allows (zero grid charges, cheapest per-unit cost), then source remaining requirements through open access. This layered approach minimises your overall electricity cost.

    4. Monitor TNERC Orders

    TNERC revises wheeling charges, CSS, and banking provisions periodically. Stay updated on regulatory changes that could affect your open access economics. TNERC orders are published at tnerc.gov.in.


    Getting Started with Open Access Solar

    Open access solar in Tamil Nadu involves regulatory complexity, commercial negotiations, and grid connectivity procedures that require experienced guidance. The key steps are:

    1. Assess your eligibility (minimum 100 kW demand for renewable open access)
    2. Evaluate captive vs third-party based on your capital availability and risk appetite
    3. Identify solar plant options (existing plants with available capacity or new project development)
    4. Model the complete cost including all charges, losses, and banking impact
    5. Apply for connectivity through TANGEDCO

    Use our solar savings calculator for an initial open access cost assessment, or contact Tristar for a detailed feasibility study tailored to your facility's consumption pattern and location.

    Ready to Go Solar?

    Get a personalized solar quote based on your electricity consumption and roof area.

    Related Articles

    We use cookies to analyse site traffic and improve your experience. Learn more